2016-04-06 / News

PLANT VOGTLE UNITS 3 AND 4 IS 60 PERCENT COMPLETE

Construction of Plant Vogtle Units 3 and 4 is 60 percent complete, based on contractual milestones, according to a statement issued last week by the Southern Company. Milestones achieved over the last 30 days include the placement of 200 cubic yards of concrete to fill the walls of new shield building panels for Unit 3; placement of more than 1,800 cubic yards of concrete to fill the walls of the CA20 module; installation of component cooling water pumps on the Unit 3 turbine building; placement of concrete for the elevated roof slab on the southwest corner of the Unit 4 turbine building and the completion of vertical seam welds on shield building panels for Unit 3